How Much Concrete Do You Need for Stairs? Steps, Landing and Bags

How many 80 lb bags does it take to pour four concrete steps and a small landing? In our example, the answer is 104 bags, or 2.29 cubic yards. That number shocks most first-time builders.

Quick Answer

A solid concrete stair with four steps (7.5 inch rise, 11 inch tread, 48 inch width), a 36 inch landing, and a 4 inch base slab needs about 61.81 cubic feet. That is 2.29 cubic yards, or roughly 104 bags of 80 lb mix. Treat each step as a stacked block, add the landing, then divide.

Why Stairs Take More Concrete Than They Look

A solid concrete stair is a stack of blocks, not a thin wedge. Step one is one rise tall, step two is two rises tall, and so on up to the top. Every block sits on a base slab, so the pour is much deeper than the steps look from the front.

The base slab is the flat layer under the steps. It is easy to forget, yet it adds volume across the whole width of the stair. That is why the totals surprise people. Four small steps and a landing can need more than two cubic yards. The diagram shows the shape we use for the math.

A solid stair as stacked blocks A side-view cross-section, not to scale. A thin slate base slab runs along the bottom. On it sit four teal blocks that are one, two, three, and four rises tall, rising left to right. At the right is an amber landing block as tall as the top step plus the slab. A strip at the bottom shows 1 + 2 + 3 + 4 = 10 rises of block in total. A solid stair is a stack of blocks on a slab Side view, not to scale 1 rise 2 rises 3 rises 4 rises base slab Landing 4 rises + slab Width runs into the page, so volume = width x side area Step blocks: 1 + 2 + 3 + 4 = 10 rises of concrete in total
Each step is one rise taller than the one before it, and all of them stand on the slab.

Our concrete stairs calculator uses this same stacked-block model. It treats the stair and the landing as two volumes, then adds them.

The Stair Volume Formula in Plain Steps

The volume comes from five short steps. Convert every length to feet first by dividing inches by 12. For metric readers, one inch is exactly 2.54 centimeters, so a 7.5 inch rise is 19.05 centimeters.

  1. Find the side-view area. A = tread x rise x n x (n + 1) / 2 + n x tread x slab, where n is the number of steps.
  2. Get the stair volume. Multiply A by the stair width.
  3. Get the landing volume. Landing = width x landing depth x (n x rise + slab).
  4. Add them. Stair plus landing gives the total in cubic feet.
  5. Convert. Divide cubic feet by 27 to get cubic yards.

The n x (n + 1) / 2 part adds up 1 + 2 + 3 and so on to n rises, because each step is one rise taller than the last. For four steps, that is 10 rises of block. A flat pad is simpler, and our guide on how much concrete for a slab covers it.

Worked Example: Four Steps and a Landing

Take four steps with a 7.5 inch rise and an 11 inch tread. The stair is 48 inches wide, the landing is 36 inches deep, and the base slab is 4 inches thick. In feet, that is a width of 4, a tread of 0.9167, a rise of 0.625, a slab of 0.3333, and a landing of 3.

  1. Side-view area. The stepped part is 0.9167 x 0.625 x 4 x 5 / 2 = 5.7292 sq ft. The slab part is 4 x 0.9167 x 0.3333 = 1.2222 sq ft. So A = 6.9514 sq ft.
  2. Stair volume. 4 x 6.9514 = 27.81 cubic feet.
  3. Landing volume. Total rise is 4 x 0.625 = 2.5 ft. Then 4 x 3 x (2.5 + 0.3333) = 34.0 cubic feet.
  4. Total. 27.81 + 34.0 = 61.81 cubic feet. Divide by 27 for 2.29 cubic yards.
Where the example concrete goes A single horizontal bar for the four-step example. The left teal part is 27.81 cubic feet for the steps. The right amber part is 34.00 cubic feet for the landing, which is more than half of the 61.81 cubic foot total. Below the bar: 2.29 cubic yards, or 104 bags of 80 lb or 138 bags of 60 lb. Where the 61.81 cubic feet go Steps 27.81 cubic feet Landing 34.00 cubic feet Total: 61.81 cubic feet = 2.29 cubic yards 104 bags (80 lb) or 138 bags (60 lb), at the calculator’s bag yields
In this example, the landing holds more concrete than the four steps.

The landing is the bigger share here, at more than half of the pour. Many builders size the steps and forget how much volume a deep landing adds.

How Step Count and Landing Depth Change the Total

Each extra step adds more concrete than the last one. With the same width, rise, tread, and slab, going from three steps to four adds about 18 cubic feet. Going from four to five adds about 20. The top step is always the tallest block, so it costs the most.

Concrete volume for 3, 4, and 5 steps Three bars that grow left to right. Three steps need 1.63 cubic yards, or 74 bags of 80 lb mix. Four steps, the worked example, need 2.29 cubic yards, or 104 bags. Five steps need 3.04 cubic yards, or 137 bags. All three include the same 36 inch landing. More steps, more concrete (same width and landing) 1.63 cu yd 2.29 cu yd 3.04 cu yd 3 steps 4 steps 5 steps 74 bags 104 bags (example) 137 bags Rise 7.5 in, tread 11 in, width 48 in, landing 36 in, slab 4 in. Bags are 80 lb.
Going from four to five steps adds more than a half cubic yard.

In bag terms, the jump is easy to see. Moving from three steps to four adds 30 bags of 80 lb mix, since 104 minus 74 is 30. Moving from four to five adds 33 bags. If your porch sits a little higher than planned, one extra step is a real cost.

The landing matters just as much. Drop it from the four-step example and the total falls from 61.81 to 27.81 cubic feet. That is 1.03 cubic yards, or 47 bags of 80 lb mix. Landing volume also grows in a straight line with its depth and with the stair width.

From Cubic Yards to Bags or Ready-Mix

Divide your cubic feet by what one bag yields, then round up. The calculator assumes an 80 lb bag yields about 0.6 cubic feet and a 60 lb bag about 0.45. Those are planning figures, so read your own bag label.

For the example, 61.81 / 0.6 = 103.0, so you need 104 bags of 80 lb. With 60 lb bags, 61.81 / 0.45 = 137.4, so you need 138. The 80 lb option means handling about 8,320 lb of dry mix.

Bagged mix versus ready-mix for the 61.81 cubic foot example
Option How it is sold Amount for the example Best fit
80 lb bags By the bag, about 0.6 cu ft each 104 bags Small pours, such as steps with no landing (47 bags)
60 lb bags By the bag, about 0.45 cu ft each 138 bags Easier to lift, but many more bags
Ready-mix By the cubic yard (27 cu ft) 2.29 cu yd Pours of about 100 bags or more

The calculator adds no waste factor. Ask your supplier how much extra to order for spills and uneven ground.

Code Limits and Rebar to Check Before You Pour

Volume is only half the plan, because the stair must also pass inspection. One county handout based on the 2018 International Residential Code lists a maximum riser of 7 3/4 inches and a minimum tread of 10 inches. Our 7.5 inch rise and 11 inch tread fit those limits.

Other city handouts that reproduce the same code say the tallest riser may not exceed the shortest by more than 3/8 inch. Adopted editions and local changes differ, so check your adopted edition with your local building office. Rise and run geometry has its own page, our stair rise and run guide.

Rebar or mesh sits in the forms before you pour, so plan it early. The rebar spacing and quantity guide shows how. For other pour shapes, try the general concrete calculator. Always measure your own forms before you order, since real forms rarely match a drawing to the inch. A small error in rise or width carries through every step of the math.

Ready to size your own pour?

Enter your rise, tread, width, and landing in the concrete stairs calculator to get cubic yards and bag counts in seconds.

FAQs About Concrete for Stairs

How many bags of concrete do I need for four steps?

With a 48 inch width, 36 inch landing, and 4 inch slab, plan on 104 bags of 80 lb mix, or 138 bags of 60 lb. Without the landing, it drops to 47 bags of 80 lb.

How many cubic yards of concrete do four steps and a landing take?

The example pour is 61.81 cubic feet, which is 2.29 cubic yards. Divide cubic feet by 27 to convert, then check the number against your own measured forms.

Should I use bagged concrete or ready-mix for stairs?

Small pours suit bags. A pour of 100 or more bags is usually ordered as ready-mix by the cubic yard, since mixing that many bags by hand is slow and heavy work.

Why does the formula use n times n plus 1, divided by 2?

Each step is one rise taller than the one before it. Adding 1 + 2 + and so on up to n rises of block gives n x (n + 1) / 2, which is 10 for four steps.

Does the calculator add extra concrete for waste?

No. The calculator adds no waste factor, so 61.81 cubic feet is the exact shape volume. Ask your supplier how much extra to order for spills and uneven ground.

What is the maximum riser height for concrete steps?

One county handout based on the 2018 IRC lists 7 3/4 inches as the maximum riser and 10 inches as the minimum tread. Codes vary, so confirm your adopted edition with your local office.

Do I count the landing separately from the steps?

Yes. The landing is its own block: width x landing depth x (total rise + slab). In the example, it adds 34.0 cubic feet to the 27.81 cubic feet for the steps.

Sources and Further Reading

References Used in This Article

This article is general education, not engineering advice. Stair codes and structural needs vary, so confirm with your local building office before you pour. Reviewed for accuracy by Prof. Dr. Khalil Mudassar, PhD. Last updated 2026-10-13.


Author

shakeel-Muzaffar
Founder & Editor-in-Chief at  ~ Web ~ More Posts

Shakeel Muzaffar is the Founder and Editor-in-Chief of MultiCalculators.com, bringing over 15 years of experience in digital publishing, product strategy, and online tool development. He leads the platform's editorial vision, ensuring every calculator meets strict standards for accuracy, usability, and real-world value. Shakeel personally oversees content quality, formula verification workflows, and the platform's commitment to publishing tools that are genuinely useful for students, professionals, and everyday users worldwide.